Timeline

Click here to skip this content
 

Please check this page frequently as information will be updated and dates added.

  • June 17, 2021
    • Fresno County received first tranche of funding in the amount of $97,031,825
  • July 13, 2021
    • ARPA presentation at the Board of Supervisors, Item #7
  • August 24, 2021
    • ARPA presentation at the Board of Supervisors, Item #7
  • August 31, 2021
    • Initial Recovery Plan Performance Report submitted to U.S. Department of the Treasury
    • Interim Finance Report submitted to U.S. Department of the Treasury
  • September – October 2021
    • Development of community outreach survey Development of Statement of Interest forms for interested organizations to submit project interest ideas
  • November – December 2021
    • Release community outreach survey (NEW – Survey Results)
    • Release Statement of Interest forms
    • U.S. Department of Treasury to release “final” rule on eligibility and program requirements (released on January 6, 2022)
    • Webinars on Statement of Interest forms
    • Development of initial ARPA funding recommendations
  • January – February 2022
    • Fresno County Board of Supervisors presentation on recommended funding allocations (February 1, 2022)
    • Compilation of community outreach survey
    • Compilation of Statement of Interest forms
    • Open application period for organizations to apply for funding
    • Webinars on application process
  • March – June 2022
    • Processing of subrecipient applications
    • Fresno County Board of Supervisors presentation on recommended subrecipient applications and earmarking/award of funding to subrecipient organizations (June 21, 2022)
  • June 21, 2022
    • Fresno County received second tranche of funding in the amount of $97,031,828
  • July 12, 2022
    • Fresno County Board of Supervisors presentation of the Recovery Plan Performance Report for year 2021
  • July – December 2022
    • Vet earmarked infrastructure investment programs related to water and sewer on the First Round Subrecipient Priority List
    • Vet earmarked programs under Category A on the First Round Subrecipient Priority List
  • November 8, 2022
    • Fresno County Board of Supervisors presentation on progress on the County’s American Rescue Plan Act- State Local Fiscal Recovery Funds, Progress Report
  • November 2022 – January 2023
    • Open second round application period for organizations and departments to apply for funding
    • Webinar on application process
  • January – July 2023
    • Processing second round subrecipient application submittals
  • August 2023
    • Fresno County Board of Supervisors presentation on recommended second round award list and earmarking/award of funding to awarded programs (August 22, 2023)
  • September – November 2023
  • December 2023 – January 2024