21-01-C Request for Clarification Responses

The following list is comprised of paraphrased Requests for Clarification (RFC) submitted by potential bidders or sub-bidders in writing via email, letter, and this form:

21-01-C Request For Clarification Form

These paraphrased questions and associated responses are not part of the contract documents and shall have no bearing whatsoever on the interpretation of the Standard Specifications, the Standard Plans, the Special Provisions, or the Plans. Nor shall they have any bearing whatsoever on the interpretation of other publications referenced therein.

Questions without answers may be posted here to indicate that we have received them before the deadline and we intend to respond. 

Last updated: 8/02/21 9:04 AM

Specification No. Notice to Bidders -3
Would it be possible to add license classification D-49/C-61 as an acceptable licensing alternative in order to bid as a Prime ? (RFC 27832 submitted 7/14/2021)

A Tree Service (D-48/C-61) license is acceptable if the contractor can self-perform the required percentage of the contract and can employ the correct classification of subcontractor capable of doing the work. See Addendum #1. Response date: 07/26/2021

Specification No. Notice to Bidders -3
There are several Determination Numbers for Tree Trimmers, would it be possible for the County to pick one that all Contractors can refer to? (RFC 27835 submitted 7/14/2021)

We cannot choose a specific determination. It appears that several classifications are required, and others are not qualified. It is the contractor's responsibility to review the scope of work and determine the appropriate classification for each item of work. Response date: 07/26/2021

Is there a completion date and how many working days/calendar days? (RFC 27861 submitted 7/16/2021)

Please refer to Special Provision Section 8-1.04B Response date: 07/16/2021

In the questions and answers you mention an addendum but I cannot find it. (RFC 28070 submitted 7/27/2021)

Addendum #1 has been posted to the project website under "Specifications and Plans." Response date: 08/02/2021